Installation Piping System/CPF


Scope of Work

Details engineering , Fabrication and Installation Piping system with Procurement the missing Materials

Testing for power Transformer

The work including but not limited the following:

  1. Design , fabrication and installation and testing piping system
  2. Supplying all missing materials such as (pipes, fitting, flanges, valves, etc.)
  3. Design, Installation and testing the flow lines between the well head and the manifolds with different sizes (6" up to 48").
  4. Installation and testing the MV and LV cables with different sizes (70 mm2 up to 500mm2) along with pipe line.
  5. Demolition and installation new piping system at the existing plants at the Garraf oil field with all the related works (testing and commissioning)
  6. Sand blasting and painting all the fabricated piping system.
  7. Supplying, fabrication and installation all kind of steel pipe supports.
  • Period

    18 months, Start: January 2012, Finish: June 2013

  • Location

    Badra Oil Field , Iraq

  • Client

    Petrofac Limited

Project Highlights