Piping and Pipeline Works – Basra


Scope of Work

The work included the following:

  1. Details Engineering
  2. Supply Fitting and valves
  3. Shop fabrication
  4. Erection the fabricated pipes
  5. NDT and Hydrotest Works
  6. Painting Testing
  7. Erection the steel structure
  8. Testing and commissioning
  • Period

    10 months, Start: December 2014, Finish: September 2015

  • Location

    Rumaila Oil Field, Basra

  • Client

    Saipem, Iraq