Piping and Pipeline Works – Basra
Scope of Work
The work included the following:
- Details Engineering
- Supply Fitting and valves
- Shop fabrication
- Erection the fabricated pipes
- NDT and Hydrotest Works
- Painting Testing
- Erection the steel structure
- Testing and commissioning
-
Period
10 months, Start: December 2014, Finish: September 2015
-
Location
Rumaila Oil Field, Basra
-
Client
Saipem, Iraq