Mechanical, Electrical and Instrumentation Works – Rumaila


Scope of Work

The work included the following:

  1. Fabrication and Installation piping and UG pipe line
  2. Installation and commissioning the Electrical works
  3. Installation all the Instrumentation Panels , Cables and Instruments ,etc.
  4. NDT Works
  5. Painting Testing
  6. Hydrostatic Test
  7. Testing and Commissioning
  • Period

    9 Months - Start: February 2014, Finish: November 2014

  • Location

    Rumaila Oil Field, Iraq

  • Client

    SIPD/CCC

Project Highlights